WWTP Upgrade Village of Harrison Hot Springs, BC

Design Build

Phase I Construction of a New MBR Waste Water Treatment plant capacity 1375m3/day dry day, max 3,000m3 24hr day  upgradeable to 5,500m3 final phase includes more than 450m3 of concrete poured, This upgrade also provides the owner with one additional 2mm screener, one 400 lbs/hr Centrifuge, a UV light system, a new diffusing system for the bioreactor, brand new 100hp blowers, all the equipment house in a new building ready to take up the last phase. The Building was constructed on an existing Equalization basin